It would be fundamental to have the ability to export a RFI schedule (downloaded) from the system to show RFI reference dates, questions and answers and parties involved, including status on the one excel sheet. At the moment we have to employ a document controller to copy and paste all of this information into a schedule - this takes time and resource!
Company | Mclaren construction |
Job Title / Role | Senior Design Manager |
I need it... | Yesterday...Come on already |
Dear Viewpoint Suggestion Box contributor;
We at Viewpoint sincerely thank you for your contribution to Suggestion Box on how we can improve Viewpoint products. While we can’t do everything at once, we rely upon your feedback to help guide the prioritization of our product improvements, and Suggestion Box is a critical tool for us to understand and prioritize our customers’ needs.
Viewpoint reviews Suggestion Box regularly for all of our products and updates statuses, adds comments, and performs various house-keeping (including deleting) as needed to ensure that Suggestion Box is maintained as a productive environment for product enhancements requests.
© 2023 Trimble Inc. All Rights Reserved. Viewpoint®, Vista™, Spectrum®, ProContractor™, Jobpac Connect™, Viewpoint Team™, Viewpoint Analytics™, Viewpoint Field View™, Viewpoint Estimating™, Viewpoint For Projects™, Viewpoint HR Management™, Viewpoint Field Management™, Viewpoint Financial Controls™, Vista Field Service™, Spectrum Service Tech™, ViewpointOne™, ProjectSight® and Trimble Construction One™ are trademarks or registered trademarks of Trimble Inc. or its affiliates in the United States and other countries. Other names and brands may be claimed as the property of others.
Like Joe says, you can add extra columns like post detail. If you then untick 'Lastest Revison' it will include all the post details including replies. The problem is that there is a limit on the number of characters displayed on the post detail column, so wont display the full question and its replies. Which brings you back to copy and paste. Please can the development team look into this and either maximise the character limit or come up with perhaps a Task dashboard like the new Workflow dashboard (you have the old 'Inbox' so why not develop the dashboard to cover all notifications?)
Hi this is achievable to most degrees - APART FROM AUTOMATICALLY giving you the response into excel. We set up all relevant column needed I a column view. ie Title; Description; From; To; Expire date, status, Post detail. Then at any point click 'Export to excel' up top middle of page and that's that. As I say unless I'm mistaken I cannot see how to get the reply into this report. However doing above at least reduces time/work to paste in the reply.